of road infrastructure

Purposive sampling was employed to select the procurement professionals, engineers while simple random sampling was adopted in selecting private consultants, members of parliament and respondents from the civil society organizations. Interviews were used to collect views from the key respondents, while data was collected using a questionnaire and analyzed using the Statistical Package for Social Scientists (SPSS).

5. Data Analysis

The analysis of data presented is based on information provided by respondents who included procurement practitioners and other key players closely involved in public procurement development. A questionnaire was administered by the researcher to 190 respondents and 172 questionnaires were received giving a response rate of 90.5%. The analysis is therefore based on the 172 questionnaires received.

Table 1 shows that 59.3% of the respondents were in the age group (30 - 40 years). Of the 172 respondents, 69.8% were male and 30.2% were female. Majori-

Table 1. Demographic characteristics.

ty of the respondents had attained a Bachelor’s degree (46.5%) and only 15.1% had attained a Master’s degree and majority of the respondents were procurement professionals (58.1%). Therefore, the results indicate that majority of the respondents had attained good education and desired skills and knowledge and therefore are able to deliver.

The results as presented in the above Table 2 indicate a high degree of rating of almost all the items that measured contractor monitoring based on the mean scores which were all above 3 on the basis of a maximum score of 5 since the survey instrument had a 5 Likert scale. This is supported by the high percentage scores on those who agreed with each of the statements. The quantitative results presented above reflect the perception of the respondents. However, there are findings from interviews and documentary reviews that give the status of contractor monitoring and how it influences the performance of road infrastructure projects.

6. Basing on Survey Findings

It was further established that 90.6% of the respondents agreed that staff designated to monitor contractors lacked adequate supervisory skills. This probably explains why some roads get into a bad state within a few months after construction. The roads according to respondents were Oluyo-Packwach-Arua Road, Entebbe road, Kampala-Jinja Road, Tororo-Mbale-Soroti, Kampala-Masaka etc. On whether UNRA had approved procedures in place for contractor monitoring, 86.9% inclined to agreement. One of the respondents noted that: “The general public is not happy because there are a lot of delays in road projects in spite of the existence of monitoring procedures”.

Furthermore, majority of the respondents (80.5%) indicated that contractor performance appraisal was not being done during the project implementation.

Table 2. Descriptive statistics for contractor monitoring.

One respondent mentioned that” contractor performance appraisal is done during project implementation and not in all agencies, but in some few”. The private consultants (57%) on the other hand had mixed responses about contractor performance appraisal being done during project implementation. They felt that the management of some public entities takes over the process hence overshadowing the contractor performance appraisal exercise.

On regular site inspection, findings further revealed that 70.7% of the respondents agreed that there are no regular on site inspections on road projects. One of the respondents noted that “at the beginning stage, the procedure for contractor monitoring should be agreed on between the contractor and employer. It is important that the relevant provisions in the instructions in relation to monitoring be applied in a consistent manner and if monitoring instructions are substantially poor, they should be revisited”.

On the issue of timely payment to contractor by government, 71.1% of the respondents observed that contractors were never paid on time and this too has a bearing on the performance of the contractor as noted by one of the respondents that: “the biggest challenges road contractors are facing is delayed payment. Certificates are approved and submitted but payment takes up to six (6) months to go through. Without adequate cash flow contractors cannot pay suppliers of materials and workers leading to projects stalling”.

The research findings further revealed that the majority, 96.3%, agreed that there are no clear dispute resolution procedures for road projects. One of the respondents noted that “It is true there are dispute resolution procedures; in case any party is aggrieved or if they are there they are not followed by UNRA”.

On management of records the findings revealed that the 94% of the respondents agreed that there is poor record management on road projects. One of the respondents noted that: “In all audits conducted by the PPDA in government agencies, the biggest problem is availability of contract management records, Section 41 of the PPDA Act, 2003 requires maintenance of procurement records for a period of seven years from the date of award or termination of the procurement or disposal and failure to archive records contravenes the legal requirement of keeping procurement records for at least seven years before deposing them off.

Some of the challenges in records management at UNRA mentioned by the respondents include; lack of awareness of the importance of proper records management practices; failure to implement UNRA records management policy and procedures; big volumes of older stored records (mainly physical records); very limited space for the physical records and lack of training in records management.

The findings also revealed that the 72.3% of the respondents agreed the contract supervisors’ failure to prepare monitoring plans. This finding concurs with [24] who noted that it is essential to development of a contract monitoring plan to ensure the contract is well monitored

Furthermore, majority of the respondents (77.7%) noted that project expectations are not clearly communicated to contractors. one of the respondents noted that “Most projects do not achieve their intended goals because the entities do not clearly communicate expectations which is bound to be disputes”. In addition, 91.5% of respondents indicated that there is lack of a clear feedback mechanism between the contractor and employer on road projects yet feedback is an important component on project success. One of the respondents noted that “concerted effort should be made to facilitate communications between all project members, not just the client and contractor but also the other stakeholders’ i.e. the public”.

Sixty nine percent (69%) of the respondents disagreed that technical audits are conducted during project implementation. This is emphasized by one of the respondents who mentioned that “although technical audits are critical on road projects, UNRA lacks the finances, personnel and equipment to conduct these audits. He noted that UNRA since its inception has conducted only two technical audits and these were done by hired experts from Kenya and Tanzania”.

The respondents were also asked whether there is quality service delivery and there was a mixed reaction with 45% agreeing to the statement. One of the respondents indicated that “there have been a lot of delays by the road contractors and so the general public is unhappy. To make matters worse, some of the contractors being awarded contracts have already been branded as inefficient”.

The respondents were asked whether there is proper contract monitoring in UNRA’ in the procurement unit, 23% of the respondents strongly disagreed and 35% strongly agreed and 16% were not sure. This confirms that a well-designed contractor monitoring process based on efficiency as laid down in the institutional theory is the way to go. There is need to build internal capacity at UNRA to conduct contractor monitoring and reduce on use of hired consultants who are costly and on several occasions was bringing down the reputation of the organization.

The respondents were asked whether there is proper contract coordination in UNRA and their responses indicated that 51% of the respondents strongly disagreed, 9% disagreed, 21% were not sure, 09% agreed and 10% strongly agreed. In relation to the above one of the respondents noted that “UNRA staff coordinate all our contracts in the best manner possible, however, sometimes we are let down by certain factors. He cited delays in paying contractors and compensating land owners as one of the key factors in project delays”. This is supported by the research findings were the 44% of the respondents strongly disagreed, 16% disagreed, 10.0% were non-committal, 20% agreed and 10% strongly agreed about the proper contract supervision in UNRA.

The results show there is a positive significant relationship at 0.000 between contractor monitoring and performance of road infrastructure projects. Therefore, improvement on the contractor monitoring will lead to a significant improvement of performance of road infrastructure projects.

7. Regression Analysis

Further analysis using regression analysis technique was made to check the level of influence of contractor monitoring on performance and results are shown in the Table 3 below.

The results in Table 4 indicate that there is a simple correlation between contractor monitoring and performance. The R2 value indicates how much of the dependent variable, performance can be explained by the independent variable contractor monitoring. In this case, 0.159 can be explained, which is very large. The standard error of the estimate is 0.1204 and the adjusted R square value is 0.841. Therefore the adjusted square value of 0.841 implied that contractor monitoring predicts performance of road infrastructure projects; in other words performance of road infrastructure projects is dependent on contractor monitoring by 84.1%.

Table 5 indicates that the regression model predicts the outcome variable significantly well. This indicates that the statistical significance of the regression model was applied. The P < 0.0005 is less than 0.05 and this indicates a significant relationship in predicting the outcome variable. F-value of 31.223 is greater than the critical F-value of 6.90 at the 0.01 level of significance. Contractor

Table 3. Relationship between contractor monitoring and performance.

**Correlation is significant at the 0.01 level (2-tailed). Source: primary data. N = 172.

Table 4. Regression analyzing the relationship between the contractor monitoring and performance.

aPredictors: (Constant), bContractor Monitoring.

aPredictors: (Constant), bContractor Monitoring.

Table 5. Analysis of variance table for contractor monitoring and performance

aPredictors: (Constant), Contractor monitoring; bDependent Variable: performance.

aPredictors: (Constant), Contractor monitoring; bDependent Variable: performance.

monitoring, therefore, predicts performance of road infrastructure projects. This implies that there is a positive relationship between contractor monitoring and performance of road infrastructure projects. The above proves that contractor monitoring influences performance of road infrastructure projects. The alternative hypothesis is therefore upheld.

8. Discussion of Results

Findings revealed that there is a positive significant relationship between contractor monitoring and performance of road infrastructure projects. This indicated that staff designated to monitor contractors lack adequate supervisory skills. Sometimes work is poorly supervised and this follows the fact that the general public has several times complained about the poor state of newly constructed roads because some roads get in a bad state a few months after construction. For example, Entebbe road, Nasser road, Oluyo-Packwach-Arua, Hima-Kasese, Kasese-Katunguru, Busega?Masaka, Jinja-Kampala etc. The general public has criticized the poor construction of Busega?Masaka, Jinja-Kampala roads where a few months after completion the roads developed potholes. This finding concurs with the study [24] who noted that best practices in government: components of an effective contract monitoring system have been a responsibility of different portfolio managers to determine the cost savings and other effects of procurement on their own.

The ability to realize procurement goals has been a fiasco in most road construction projects due to poor contractor monitoring in spite of UNRA contracting international road supervision Consultants. There are gross delays of roads construction completion and shoddy work in Uganda. This has, therefore, created contract monitoring gaps in terms of acting in stake holder interests, client/employer communication, negotiation, contract management, dispute resolution and approvals of changes and authorization [20] in his study on the ‘critical success factors in government contract management’ noted that qualified workforce, clear processes, relationships, resources, leadership and policies as critical success factors for contract management. All these have a direct impact on an organization’s contract management process as well as resulting outcomes.

[2] noted that contract monitoring is essential for achieving the most profitable benefits from supplier relationships and to optimize total costs of the procurement function. However, when a party is aggrieved he/she can seek administrative review [25] defines administrative review as a clear dispute resolution procedures for road projects. This is asserted by [26] that in a theoretical underpinning of the challenges of contractor monitoring in Canada, the important issue in monitoring a supplier’s performance is deciding who is best placed to actually monitor that performance. The supplier’s performance must be assessed objectively against criteria that are pre-determined, clearly understood and agreed upon by both parties in the conditions of the contract so that the party does not seek administrative review.

Furthermore regarding quality service delivery, 65% of the respondents appreciated that UNRA’s mandate is not an easy task. The public expects quite a lot from the institution irrespective of the constraints it may face. UNRA is a young institution that faces an enormous assignment of developing and maintaining our roads and ensuring they are in a better condition. This is consistent with [27] finding that the main aim of contract monitoring is to ensure that goods or services are delivered on time, at the agreed cost. This implies developing effective working relationships with your suppliers, ensuring effective service delivery and providing consistent quality for stakeholders and end users [28] . The primary goal for contractor monitoring within any company is to ensure that commitments and obligations to customers and suppliers are clearly visible to the relevant people in the organization and that they are executed upon [27] . Contracts are used to control virtually every part of the trading relationship between buyers, sellers, and intermediaries, and have an impact on various functions within the enterprise [2] . For example, the sell-side involves sales, marketing, finance, legal, sales operations and customer service.

The findings further revealed that the lowest bid acquisition in UNRA has encouraged underperformance by the contractors who are in competition with other low-bid contractors. Under the low-bid acquisition methods used by UNRA, sometimes, contractors under price a bid in order to win a contract. To recover their lost profits, contractors then use substandard materials, poor workmanship, and take great risks to the health and safety of their laborers. Lowest bid contracting used by UNRA on roads has paved way to contracting poor contractors who perform shoddy work. According to [28] effectiveness of contract management in Austria requires the systematic management of contract creation, execution, compliance and analysis to maximize performance and minimize risk. With the increase in the complexity of doing business in public entities, coupled with the increase in transaction volumes and value in an ever tightening regulatory framework, it has resulted in businesses taking note of the importance of proper monitoring of contractor [8] .

It was observed that at the procurement stage, some companies have also often been quoting lower bids, however, after winning the contracts they seek for variations causing the cost overrun. Contractor monitoring is the active control of the contract between the procuring and disposing entity and the contractor, in order to ensure delivery of a cost effective and reliable service at an agreed standard and price. It is the final stage in the bidding process and marks the beginning of a contractual relationship between the procuring and disposing entity and contractor in the process of managing and administrating the contract implementation [29] . Contractor monitoring cycle is the process of systematically and efficiently managing contract creation, execution and analysis for maximizing operational and financial performance and minimizing risk [30] while [31] his study on compliance monitoring and procurement performance carried out in Uganda, notes that supplier/contractor monitoring has slowly become an important component for effective supplier relationship management that is directly linked to securing the supply of key commodities needed for sustaining business.

The reports from UNRA further confirmed that although project unit cost for road construction projects greatly varied from project to project, the average cost per km of double bituminous surface treatment upgrading works had reduced from UGX 2.05 billion to UGX 1.84 billion. A total of 1255 km roads were upgraded/rehabilitated/reconstructed, and over 20,000 kms received periodic and routine maintenance mainly by private local contractors [23] .

Findings reveal that there was delayed completion of works by the contractor for over 10 weeks without the employer’s intention to charge for delayed damages. This is noted on the Kawempe-Kafu Road (166 Km) by M/s Energoprojekt Niskogradnja at UGX. 140,556,490,385. Notwithstanding the above findings, UNRA disregarded a recommendation in the FY 2008/09 audit report to defer application of the overlay since underlying layers were weak; more than UGX.140,556,490,385 was to be spent yet the works had shown signs of distress [17] .

[14] investigated the causes of construction project delays and cost overruns in Uganda’s public sector with an intention of ranking them according to their frequency, severity and importance. A total of 30 projects at Civil Aviation Authority were reviewed. Five most important causes of delays and cost overruns were found to be changes in the work scope, delayed payments to contractors, poor monitoring and control, high inflation and interest rates. [29] examined the relationship between supplier opportunism, contract management and service delivery in outsourced contracts in Uganda. The study was conducted in the 116 Procuring and Disposing Entities in Uganda and the findings reveal that supplier opportunism and contract management are significant predictors of service delivery. This study, however, does not address the impact of supplier determination process on contract performance.

It was observed that the coordination of contracts involves many activities to ensure the fulfillment of a contract. This covers those activities or events that can alter or disrupt the performance of a contract e.g., default of a contractor, disputes and contract amendments. Whenever the satisfactory fulfillment of a contract is jeopardized, UNRA sometimes takes the necessary steps to serve and protect the interests of the institution in meeting the terms of the contract, and then to protect (where appropriate) the interests of other parties involved in the contract.

9. Conclusions, Recommendations and Policy Implications

For effective road infrastructure delivery and performance, there is need to build strong contract monitoring mechanisms. These should target the performance of contractors and contract managers/supervisors. With skilled personnel proper contract monitoring practices shall be enforced. In contract monitoring some of the components and practices include skills development, policy development, plans, communication, payments, management of records, contractor appraisal, inspections and audits and dispute resolution. This study found out that if these contract monitoring components are well managed, there is a very high possibility of having a viable road infrastructure project that will guarantee a sound business success and effective service delivery.

In order to improve contractor monitoring and performance of road infrastructure projects the researcher makes the following recommendations:

The procurement rules should be adjusted to allow best value contracting method, such as award contracts based on demonstrated past performance, technical and managerial merit, technical innovation, and financial health over and above the contractor’s price.

All contractors monitoring should be done by appropriately qualified personnel with competence and experience in road projects.

Uganda National Roads Authority should adopt systems that appraise both contractors and contract supervisors with clear disciplinary actions for unsatis- factory performance, professionalize management of records and develop a re- cords management code of ethics, establish a clear chain of communication to ensure timely input and distribution on the projects and undertake technical audits to enhance the quality of road construction. These should be conducted by the qualified professional engineers with experience in highway designing, construction and contract management.

The Government should allocate adequate financial resources to UNRA to ensure timely payment of contractors to enhance timely services delivery and also consider setting up an Independent Public Infrastructure Development and Monitoring Unit with specialized skills to provide support in Road infrastruc- ture planning, procurement monitoring.

The researcher theorises that one critical area could be due contractor monitoring and no deliberate effort has been made by researchers to link contractor monitoring to the performance of the road projects in Uganda. This has created a knowledge gap.

Cite this paper
Byaruhanga, A. and Basheka, B. (2017) Contractor Monitoring and Performance of Road Infrastructure Projects in Uganda: A Management Model. Journal of Building Construction and Planning Research, 5, 30-44. doi: 10.4236/jbcpr.2017.51003.
References

[1]   Benamghar, L. and Limi, A. (2011) Efficiency in Public Procurement in Rural Road Projects in Nepal. World Bank Policy Research Working Paper No. 5736.
https://doi.org/10.1596/1813-9450-5736

[2]   Arrows, S. (2010) Horizontal Policies in Public Procurement. Journal of Public Procurement, 10, 149-186.

[3]   Wasike, W.S. (2001) Road Infrastructure Policies in Kenya: Historical Trends and Current Challenges. Kenya Institute for Public Policy Analysis Working Paper No. 1, Nairobi.

[4]   Orr, J. and Kennedy, R. (2008) Highlights of Recent Trends in Global Infrastructure: New Players and Revised Game Rules. Transnational Corporations, 17, 95.

[5]   KPMG (2013) International Annual Review.
https://home.kpmg.com/content/dam/kpmg/pdf/2013/12/internation
al-annual-review-2013.pdf

[6]   Deustche Bank (2012).
https://annualreport.deutsche-bank.com/2012/ar/servicepages/down
loads/files/dbfy2012_entire.pdf

[7]   World Bank (2011) Comparative Analysis of Public Finance Management Reforms. World Bank, Washington DC.

[8]   Bagaka, O. and Kobia, M. (2010) Enhancing Trust and Accountability in Government. CAPAM African Regional Conference, Abuja, 18 May 2010.

[9]   Barasa, H. (2014) Procurement Practices Affecting Effective Public Projects Implementation in Kenya; A Case Study of Kenya Civil Aviation Authority. European Journal of Business and Management, 6, 49.

[10]   Banaitiene, N. and Banaitis, A. (2006) Analysis of Criteria for Contractors. Taylor and Francis Group, Abingdon-on-Thames, 276-282.

[11]   UNRA (2008) 5 Year Strategic Plan. UNRA, Kampala.

[12]   ACODE (2012) Assessing Governance Aspects in the Water and Roads Sectors in Uganda. ACODE, Kampala.

[13]   Inspectorate of Government (2012) The Third Annual Report on Tracking Corruption Trends in Uganda Using the Data Tracking System. Kampala.
https://www.igg.go.ug/static/files/publications/Third_DTM_Report
_Final_12Dec2012__2_1.pdf


[14]   Ministry of Works and Transport (2011) Annual Performance Review Report. Kampala.

[15]   Alinaitwe, H., Apolot, R. and Tindiwensi, D. (2013) Investigation into the Causes of Delays and Cost Overruns in Uganda’s Public Sector Construction Projects. Journal of Construction in Developing Countries, 18, 33-47.

[16]   Uganda Road Fund (2015) Road Maintenance Monitoring Report. Kampala.

[17]   Office of the Auditor General (2010) Annual Report. Kampala.

[18]   Kasaija, M. (2015) Budget Speech Financial Year 2015/16. Ministry of Finance, Planning and Economic Development, Kampala.

[19]   Muhakanizi, K. (2005) The State of Public Service Delivery in Uganda; Achievements Challenges and Measures for Better Service Delivery. Serena International Conference Centre, Kampala.
http://budget.go.ug/budget/sites/default/files/PSST%20Presentation
%20on%20%20Service%20Delivery.pdf


[20]   Rendon, R. (2010) Critical Success Factors in Government Contract Management.
http://www.ippa.org/IPPC4/Proceedings/19Others/Paper19-2.pdf

[21]   Oluka, P. and Basheka, B. (2014) Determinants and Constrains to Effective Procurement Contract Management in Uganda; A Practioner’s Prespective. International Journal of Logistics Systems and Management, 17, 104-124.
https://doi.org/10.1504/IJLSM.2014.057983

[22]   Booth, D. and Mutebi, F.-G. (2015) Reforming the Roads Sector in Uganda; A Six Year Retrospective.

[23]   Ssebanakitta, P. (2013) Impact of Procurement Reforms on Procurement of Works in Uganda. Journal of Public Procurement and Contract Management, 110-105.

[24]   Hinton (2003) Best Practices in Government: Components of an Effective Contract Monitoring System.

[25]   PPDA (2015) Administrative Review Guidelines. Kampala.

[26]   Hansson, S.O. (2013) Decision Theory: A Brief Introduction. Department of Philosophy and the History of Technology, Royal Institute of Technology, Stockholm.
http://people.kth.se/~soh/decisiontheory.pdf

[27]   Schmitz, J. and Platts, K. (2004) Supplier Logistics Performance Measurement: Indications from a Study in the Automotive Industry. International Journal of Production Economics, 89, 231-243.

[28]   Hatush, Z. and Skitmore, M. (2009) Evaluating Contractor Prequalification Data: Selection Criteria and Project Success Factors. Construction Management Economics, 15, 129-147.

[29]   Ahimbishibwe, A. and Muhwezi, M. (2015) Contract Management, Inter Functional Coordination, Trust and Contract Performance of Works Contracts in Ugandan Public Procuring and Disposing Entities. European Journal of Business and Management, 7.

[30]   Sabiiti, C.K., Muhumuza, E. and Basheka, B.C. (n.d.) Developing Public Procurement Performance Measurement Systems in Developing Countries: The Uganda Experience. International Public Procurement Conference.
http://www.ippa.org/IPPC4/Proceedings/12ProcurementPerformance/Paper12-1.pdf

[31]   Mbalangu, G. (2015) Supply Chains: Some Doubts. International Purchasing and Supply Education and Research Association. Cardiff.

 
 
Top