 JFRM  Vol.6 No.1 , March 2017
Construction and Operation of the Fehmarn Belt Immersed Tunnel Is a High-Risk Business Case
Abstract: The Fehmarn Belt immersed tunnel project conditionally approved by the Danish parliament on 28 April 2015 is supposed to be built and commercially operated by a Danish state owned company and financed by loans guaranteed by the Danish government. The loans are going to be amortized by incomes from the tunnel users. According to plans construction work was supposed to start by 2016 followed by tunnel inauguration in 2022, this has been put on hold awaiting clarification of major uncertainty issues. Since the official financial model is publicly unavailable, the uncertainty profiles presented in this paper are based on a financial model developed by the author covering 60 years of future tunnel operation and validated in terms of project payback period (PBP) compared to published results generated by the official model. Uncertainty is represented and calculated by probabilistic uncertainty representation and Monte Carlo simulation as well as interval analysis. The resulting project uncertainty profiles are presented in terms of a traffic light metaphor: Green light corresponds to a payback period less than 40 years, yellow to 40-50 years, and red to larger than 50 years. It turns out that the tunnel project constitutes a high-risk business case and the likelihood of financial project failure in terms of the payback period being outside of the green light zone is substantially larger than acknowledged by the project proponents and presented to the public. This is primarily due to apparently too optimistic base case assumptions of critical, but uncertain, project variables and methodologically insufficient partial sensitivity analyses.
Cite this paper: Schjær-Jacobsen, H. (2017) Construction and Operation of the Fehmarn Belt Immersed Tunnel Is a High-Risk Business Case. Journal of Financial Risk Management, 6, 1-15. doi: 10.4236/jfrm.2017.61001.
References

[1]   Andersen, K. E. (2015). Analysis of New Traffic Forecasts of the Fehmarn Fixed Link. Copenhagen: Praxis. (In Danish)

[2]   COWI (2015). External Quality Assurance of the Updated Traffic Prognosis of the Fehmarn Belt Project. Ministry of Transport. (In Danish)

[3]   Danish Parliament (2009). Planning of a Fixed Link Crossing Fehmarn Belt with Connecting Land Works in Denmark. Planning Act No. 285. (In Danish)

[4]   Danish Parliament (2015). Construction and Operation of a Fixed Link Crossing Fehmarn Belt with Connecting Land Works in Denmark. Proposal of Construction Act L141. (In Danish)

[5]   DIW Econ GmbH (2015a). Report on the Latest Traffic Forecast for the Fehmarn Belt Fixed Link. Berlin: Commissioned by Scandlines. (In German)

[6]   DIW Econ GmbH (2015b). How Robust Are the Profitability Analyses of the Fixed Fehmarn Belt Link?—Financial Model and Cost-Benefit Analysis on the Test Bench. Berlin: Commissioned by Scandlines. (In German)

[7]   Femern A/S (2014a). Traffic Forecast of a Fixed Link Crossing Fehmarn Belt. (In Danish)

[8]   Femern A/S (2014b). Financial Analysis of the Fehmarn Belt Fixed Link including Danish Land Works. (Official Translation of Original Danish Report).

[9]   Femern A/S (2015). Status of Construction Budget for the Fixed Link across the Fehmarnbelt. (Official Translation of Original Danish Document).

[10]   Femern A/S (2016). Official Home Page. www.femern.com

[11]   Flyvbjerg, B. (2006). From Nobel Prize to Project Management: Getting Risks Right. Project Management Journal, 37, 5-15.

[12]   Flyvbjerg, B., & COWI (2004). Procedures for Dealing with Optimism Bias in Transport Planning. Guidance Document, British Department for Transport.

[13]   Flyvbjerg, B., Garbuio, M., & Lovallo, D. (2009). Delusion and Deception in Large Infrastructure Projects: Two Models for Explaining and Preventing Executive Disaster. California Management Review, 51, 170-193.
https://doi.org/10.2307/41166485

[14]   FTC (Fehmarnbelt Traffic Consortium) (1999). Fehmarn Belt Traffic Demand Study. Final Report.

[15]   FTC (Fehmarnbelt Traffic Consortium) (2003). Fehmarn Belt forecast 2002. Final Report.

[16]   HyvÖnen, E., & de Pascale, S. (2000). Interval Solver 2000 for Microsoft Excel. User’s Guide, Version 4.0, Helsinki: Delisoft Ltd.

[17]   Intraplan Consult GmbH and BVU Beratergruppe GmbH (2014a). Fehmarnbelt Forecasts 2014—Update of the FTC-Study of 2002.

[18]   Intraplan Consult GmbH and BVU Beratergruppe GmbH (2014b). Fehmarnbelt Forecasts 2014—Update of the FTC-Study of 2002, Annex.

[19]   Intraplan Consult GmbH and BVU Beratergruppe GmbH (2015). Addendum to the Fehmarnbelt Forecasts 2014—Update of the FTC-Study of 2002 Referring to Additional Data and Statements Provided by Scandlines in January 2015.

[20]   Lorentzen, K. P. (2015). Quotation from Speech in the Danish Parliament on the Occasion of the First Readings of L141, Folketingstidende. (In Danish)
http://www.folketingstidende.dk/RIpdf/samling/20141/forhandlinger/M65/20141_M65_helemoedet.pdf#nameddest=L141

[21]   LR Consulting (2015a). An Evaluation of the Project Economy for a Fixed Link Crossing Fehmarn Belt. (In Danish) www.lrc.dk

[22]   LR Consulting (2015b). Simulation of Effect of Changes in the Fehmarn Belt Project Forecast Assumptions for 5 Vital Parameters. (In Danish) www.lrc.dk

[23]   Lundberg, M., Jenpanitsub, A., & Pyddoke, R. (2011). Cost Overruns in Swedish Transport Projects. Working Paper 2011:11, Sweden: Centre for Transport Studies, KTH Royal Institute of Technology.

[24]   Palisade Corporation (2013). @RISK, Version 6.1, Monte Carlo Add-In Module for MS Excel. www.palisade.com/risk

[25]   Scandlines (2015a). The Femern A/S Prognosis from November 2014 Compared to Factual Development. Letter from Scandlines ApS, Denmark, to the Danish Transport Commission. (In Danish)

[26]   Scandlines, (2015b). Scandlines RØdby-Puttgarden Traffic Volume 1998-2014. (In Danish)
http://www.scandlines.dk/om-scandlines/fast_forbindelse.aspx

[27]   Schjær-Jacobsen, H. (1996). A New Method for Evaluating Worst- and Best-Case (WBC) Economic Consequences of Technological Development. International Journal of Production Economics, 46-47, 241-250.
https://doi.org/10.1016/0925-5273(95)00159-X

[28]   Schjær-Jacobsen, H. (2002). Representation and Calculation of Economic Uncertainties: Intervals, Fuzzy Numbers, and Probabilities. International Journal of Production Economics, 78, 91-98.
https://doi.org/10.1016/S0925-5273(00)00167-5

[29]   Schjær-Jacobsen, H. (2004). Modeling of Economic Uncertainty. Fuzzy Economic Review, 9, 49-73.

[30]   Schjær-Jacobsen, H. (2010). Numerical Calculation of Economic Uncertainty by Intervals and Fuzzy Numbers. Journal of Uncertain Systems, 4, 47-58.

[31]   Schjær-Jacobsen, H. (2013). Aleatory and Epistemic Modeling of Uncertainty for Quantitative Simulations. In E. Gil-Lafuente, et al. (Eds.), Decision Making Systems in Business Administration (pp. 373-383). Singapore: World Scientific.
https://doi.org/10.1142/9789814452052_0031

[32]   Schjær-Jacobsen, H. (2014). Modeling Economic Project Uncertainty: Beware of Best Practice. 18th Working Seminar on Production Economics, 4, 225-236.

[33]   Schjær-Jacobsen, H. (2016). Construction and Operation of the Fehmarn Belt Immersed Tunnel Is a High Risk Business Case. 19th Working Seminar on Production Economics, 1, 367-378.

[34]   Statistikbanken (2015). Passenger Car Traffic RØdby Færgehavn—Puttgarden. (In Danish)
http://www.statistikbanken.dk/statbank5a/default.asp?w=1600

[35]   TRM—Danish Ministry of Transport (2004). Fixed Link across Fehmarnbelt—Financial Analysis.

[36]   TRM—Danish Ministry of Transport (2006). Document No. 16 Communicated to the Finance Committee from the Minister of Transport, Denmark. (In Danish)

[37]   TRM—Danish Ministry of Transport (2010). New Budgeting in the Ministry of Transport, Including Model of Financial Control and Risk Management for Construction Projects. (In Danish)

[38]   TRM—Danish Ministry of Transport (2015). Quotation of the Minister of Transport in Press Release 12 November. (In Danish)

 
 
Top