Risks Evaluation of Sahand New Town 1226 Housing Project and Exploring Their Effects on Time and Cost of the Project
ABSTRACT
The main objective of this research is Risks Evaluation of Sahand New Town 1226 housing Project by means of Project Management Body of Knowledge (PMBOK) model in Iran. PMBOK presents a set of standards and guidelines for project management. After reviewing the literatures, 22 risk items have been identified. 19 risks were finalized under 5 factors of Administrative, environmental, economic and political and organizational using exploratory analysis. Technique for Order of Preference by Similarity to Ideal Solution (TOPSIS) method under four criteria cost, time, quality and safety was used to select 2 work packages as the most important work packages. Consequently, the activities of the selected work packages were obtained via opinion’s experts. Then, the risks were categorized into direct risks and indirect risks using semi-structural interview with experts. Results showed that financial risk was known as most important indirect threat and risk of delay in supply and mistakes in construction were the most important direct threat. Finally, the impact of risks on time and cost of the project were obtained as the follow: the project with 90% probability would finish with 29.39 months delay. Similarly, with 90% probability will have 4003.837IRR increase in cost.

Cite this paper
Salimi, R. , Yarmohammadi, Y. , Masomi, A. and Heydari Farasani, H. (2015) Risks Evaluation of Sahand New Town 1226 Housing Project and Exploring Their Effects on Time and Cost of the Project. Journal of Service Science and Management, 8, 754-765. doi: 10.4236/jssm.2015.85076.
References
[1]   Nieto-Morote, A. and Ruz-Vila, F. (2011) A Fuzzy Approach to Construction Project Risk Assessment. International Journal of Project Management, 29, 220-231.
http://dx.doi.org/10.1016/j.ijproman.2010.02.002

[2]   Cooper, D.F., Grey, S., Raymond, G. and Walker, P. (2005) Project Risk Management Guidelines: Managing Risk in Large Projects and Complex Procurements. John Wiley & Sons, Ltd., England, 384.

[3]   Chapman, C. and Ward, S. (1996) Project Risk Management: Processes, Techniques and Insights. John Wiley.

[4]   Barker, C.F. and Campbell, C.B. (2000) Risk Management in Total System Ship Design. Naval Engineers Journal, 112, 355-365.
http://dx.doi.org/10.1111/j.1559-3584.2000.tb03342.x

[5]   Raz, T. and Michael, E. (2001) Use and Benefits of Tools for Project Risk Management. International Journal of Project Management, 19, 9-17.
http://dx.doi.org/10.1016/S0263-7863(99)00036-8

[6]   Assaf, S.A. and Al-Hejji, S. (2006) Causes of Delay in Large Construction Projects. International Journal of Project Management, 24, 349-357.
http://dx.doi.org/10.1016/j.ijproman.2005.11.010

[7]   Chicken, J.C. and Posner, T. (1998) The Philosophy of Risk. Vol. 21, Thomas Telford, London.

[8]   Kaplan, S. and Garrick, B.J. (1981) On the Quantitative Definition of Risk. Risk Analysis, 1, 11-27.
http://dx.doi.org/10.1111/j.1539-6924.1981.tb01350.x

[9]   Chapman, C.B. and Cooper, D.F. (1983) Risk Analysis: Testing Some Prejudices. European Journal of Operational Research, 14, 238-247.
http://dx.doi.org/10.1016/0377-2217(83)90260-6

[10]   Motawa, I.A., Anumba, C.J. and El-Hamalawi, A. (2006) A Fuzzy System for Evaluating the Risk of Change in Construction Projects. Advances in Engineering Software, 37, 583-591.
http://dx.doi.org/10.1016/j.advengsoft.2006.01.006

[11]   Choi, H.H. and Mahadevan, S. (2008) Construction Project Risk Assessment Using Existing Database and Project-Specific Information. Journal of Construction Engineering and Management, 134, 894-903.
http://dx.doi.org/10.1061/(ASCE)0733-9364(2008)134:11(894)

[12]   North, D.W. (1995) Limitations, Definitions, Principles and Methods of Risk Analysis. Revue Scientifique et Technique/Office International des Epizooties, 14, 913-924.

[13]   Raz, T. and Michael, E. (2001) Use and Benefits of Tools for Project Risk Management. International Journal of Project Management, 19, 9-17.
http://dx.doi.org/10.1016/S0263-7863(99)00036-8

[14]   Hillson, D. (2002) Use a Risk Breakdown Structure (RBS) to Understand Your Risks. Proceedings of the Project Management Institute Annual Seminars & Symposium, Vol. 10, San Antonio, 3-10 October 2002.

[15]   Dorofee, A.J., Walker, J.A., Alberts, C.J., Higuera, R.P. and Murphy, R.L. (1996) Continuous Risk Management Guidebook. Carnegie-Mellon University Software Engineering Institute, Pittsburgh, 562.

[16]   Chapman, R.J. (2001) The Controlling Influences on Effective Risk Identification and Assessment for Construction Design Management. International Journal of Project Management, 19, 147-160.
http://dx.doi.org/10.1016/S0263-7863(99)00070-8

[17]   Dikmen, I. and Birgonul, M.T. (2006) An Analytic Hierarchy Process Based Model for Risk and Opportunity Assessment of International Construction Projects. Canadian Journal of Civil Engineering, 33, 58-68.
http://dx.doi.org/10.1139/l05-087

[18]   Hillson, D. (2002) Extending the Risk Process to Manage Opportunities. International Journal of Project Management, 20, 235-240.
http://dx.doi.org/10.1016/S0263-7863(01)00074-6

[19]   Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997) Factors Influencing Construction Time and Cost Overruns on High-Rise Projects in Indonesia. Construction Management & Economics, 15, 83-94.
http://dx.doi.org/10.1080/014461997373132

[20]   Mulholland, B. and Christian, J. (1999) Risk Assessment in Construction Schedules. Journal of Construction Engineering and Management, 125, 8-15.
http://dx.doi.org/10.1061/(ASCE)0733-9364(1999)125:1(8)

[21]   Dey, P.K. (2002) Project Risk Management: A Combined Analytic Hierarchy Process and Decision Tree Approach. Cost Engineering, 44, 13-27.

[22]   Wang, S.Q., Dulaimi, M.F. and Aguria, M.Y. (2004) Risk Management Framework for Construction Projects in Developing Countries. Construction Management and Economics, 22, 237-252.
http://dx.doi.org/10.1080/0144619032000124689

[23]   Zou, P.X., Zhang, G.M. and Wang, J.Y. (2007) Understanding the Key Risks in Construction Projects in China. International Journal of Project Management, 25, 601-614.
http://dx.doi.org/10.1016/j.ijproman.2007.03.001

[24]   Mousavi, S.M., Tavakkoli-Moghaddam, R., Azaron, A., Mojtahedi, S.M.H. and Hashemi, H. (2011) Risk Assessment for Highway Projects Using Jackknife Technique. Expert Systems with Applications, 38, 5514-5524.
http://dx.doi.org/10.1016/j.eswa.2010.10.085

[25]   Cagliano, A.C., Grimaldi, S. and Rafele, C. (2011) A Systemic Methodology for Risk Management in Healthcare Sector. Safety Science, 49, 695-708.
http://dx.doi.org/10.1016/j.ssci.2011.01.006

[26]   Ergu, D., Kou, G., Shi, Y. and Shi, Y. (2014) Analytic Network Process in Risk Assessment and Decision Analysis. Computers & Operations Research, 42, 58-74.
http://dx.doi.org/10.1016/j.cor.2011.03.005

[27]   Yildiz, A.E., Dikmen, I., Birgonul, M.T., Ercoskun, K. and Alten, S. (2014) A Knowledge-Based Risk Mapping Tool for Cost Estimation of International Construction Projects. Automation in Construction, 43, 144-155.
http://dx.doi.org/10.1016/j.autcon.2014.03.010

[28]   Taylan, O., Bafail, A.O., Abdulaal, R. and Kabli, M.R. (2014) Construction Projects Selection and Risk Assessment by Fuzzy AHP and Fuzzy TOPSIS Methodologies. Applied Soft Computing, 17, 105-116.
http://dx.doi.org/10.1016/j.asoc.2014.01.003

[29]   Taklif, A., Shokouhian, R., Arasteh, A.S. and Dalfard, V.M. (2011) Quantifying Risk Analysis Using Database in Industrial Investment Projects by Topsis Method. Indian Journal of Science and Technology, 4, 779-784.

[30]   Teimoorirad, M. and Azizi, A.R. (2013) Identification and Evaluation of the Risks of Information and Communication Technology Projects, Shiraz. Journal of System Management, 1, 91-109.

[31]   Tah, J.H.M. and Carr, V. (2001) Towards a Framework for Project Risk Knowledge Management in the Construction Supply Chain. Advances in Engineering Software, 32, 835-846.
http://dx.doi.org/10.1016/S0965-9978(01)00035-7

[32]   Zeng, J.H., An, M. and Smith, N.J. (2007) Application of a Fuzzy Based Decision Making Methodology to Construction Project Risk Assessment. International Journal of Project Management, 25, 589-600.
http://dx.doi.org/10.1016/j.ijproman.2007.02.006

[33]   Ebrahimnejad, S., Mousavi, S.M. and Seyrafianpour, H. (2010) Risk Identification and Assessment for Build-Operate-Transfer Projects: A Fuzzy Multi Attribute Decision Making Model. Expert Systems with Applications, 37, 575-586.
http://dx.doi.org/10.1016/j.eswa.2009.05.037

[34]   Carbone, T.A. and Tippett, D.D. (2004) Project Risk Management Using the Project Risk FMEA. Engineering Management Journal, 16, 28-35.
http://dx.doi.org/10.1080/10429247.2004.11415263

[35]   Yeo, K.T. (1990) Risks, Classification of Estimates and Contingency. Journal of Management in Engineering, 6, 458-470.
http://dx.doi.org/10.1061/(ASCE)9742-597X(1990)6:4(458)

 
 
Top