 CUS  Vol.9 No.1 , March 2021
How Would the Trackless Tram System and Public-Private Partnership (PPP) Apply to Bulawayo?
Abstract: The City of Bulawayo urgently needs to rebuild its dilapidated infrastructure and stimulate its economic activities. A Public-Private Partnership funding mechanism could enable the implementation of Trackless Trams on its corridors bringing mobility, a new solar power system and other multiple economic and social benefits, especially demonstrating the intention of Bulawayo to leapfrog into a 21st century future. This study designs a PPP model referred to as a Three Multifaceted PPP Model (TMPM) that will enable the implementation of the Trackless Tram project in Bulawayo. The TMPM model is composed of three layers of players each required to structure a separate PPP arrangement. The city council would lead the first layer responsible for road construction. The real estate developers would lead the second layer and be responsible for constructing station precincts especially the construction of a solar-based Transit Mall. The Trackless Tram consortium and public transport agency will manage the third layer that provides and operates the trams. The split of the project into three layers should enable its quicker delivery by lowering capital risk through spreading it over a number of players. Climate finance could be tapped. This model should be replicable to other developing cities.
Cite this paper: Ndlovu, V. and Newman, P. (2021) How Would the Trackless Tram System and Public-Private Partnership (PPP) Apply to Bulawayo?. Current Urban Studies, 9, 17-30. doi: 10.4236/cus.2021.91002.
References

[1]   Bhoroma, V. (2020). PPPs Ideal for Self-Financing Infrastructure Projects. Bulawayo24.
https://bulawayo24.com/index-id-opinion-sc-columnist-byo-179915.html#.XlPnLnAhQTU.email

[2]   City of Bulawayo (2020a). Corporate Strategy 2020-2024.
http://citybyo.co.zw/Downloads/Policies

[3]   City of Bulawayo (2020b). Report of Study—Master Plan 2019-2034.
http://citybyo.co.zw/Downloads/Policies

[4]   Colin Buchanan and Partners (2002). Guide to Contracts and Contracting in the European Union. Report for the European Commission, London: Colin Buchanan and Partners.

[5]   Dauskardt, R., & Ganguly, S. (2020). Designing the African Development Bank’s PPP Framework: Whitepaper for Discussion. Abidjan: African Development Bank (AfDB).
https://www.afdb.org/sites/default/files/2020/09/15/afdb_ppp_framework_whitepaper.pdf

[6]   Dube, C., & Chigumira, G. (2010). The Scope for Public-Private Partnerships for Infrastructure Development in Zimbabwe.
http://www.zeparu.co.zw/sites/default/files/2018-09/2010Working%20paper_ The%20scope%20for%20PPPs%20in%20Zimbabwe_Revised%20Draft.pdf

[7]   International Telecommunication Union (ITU) (2014). Speeches by ITU Secretary-General, Dr Hamadoun I. Touré. ITU.
http://www.itu.int/en/osg/Pages/speeches.aspx

[8]   Kazunga, O. (2019). Bulawayo Dreams of “Trackless Tram”. Bulawayo.
https://www.chronicle.co.zw/bulawayo-dreams-of-trackless-tram

[9]   Kennedy, C., Stewart, I. D., Westphal, M. I., Facchini, A., & Mele, R. (2018). Keeping Global Climate Change within 1.5 ℃ through Net Negative Electric Cities. Current Opinion in Environmental Sustainability, 30, 18-25.
https://doi.org/10.1016/j.cosust.2018.02.009

[10]   Mandri-Perrott, C., & Menzies, I. (2010). Private Sector Participation in Light Rail-Light Metro Transit Initiatives. World Bank Group.
https://doi.org/10.1596/978-0-8213-8085-7
http://documents.worldbank.org/curated/en/355141468323976491/Private-sector-participation-in-light-rail-light-metro-transit-initiatives

[11]   Masson-Delmotte, V., Zhai, P., Pörtner, H.-O., Roberts, D., Skea, J., Shukla, P. R., Pirani, A., Moufouma-Okia, W., Péan, C., Pidcock, R., Connors, S., Matthews, J. B. R., Chen, Y., Zhou, X., Gomis, M. I., Lonnoy, E., Maycock, T., Tignor, M., & Waterfield, T. (2019). IPCC, 2018: Global Warming of 1.5 ℃. An IPCC Special Report on the Impacts of Global Warming of 1.5 ℃ above Pre-Industrial Levels and Related Global Greenhouse Gas Emission Pathways, in the Context of Strengthening the Global Response to the Threat of Climate Change, Sustainable Development, and Efforts to Eradicate Poverty.

[12]   Mbiba, B., & Ndubiwa, M. (2008). Decent Work in Construction and the Role of Local Authorities: The Case of Bulawayo City, Zimbabwe.
http://eprints.lse.ac.uk/3015/

[13]   Meidutē, I., & Paliulis, N. K. (2011). Feasibility Study of Public-Private Partnership. International Journal of Strategic Property Management, 15, 257-274.
https://doi.org/10.3846/1648715X.2011.617860

[14]   Ndlovu, V., & Newman, P. (2020). Leapfrog Technology and How It Applies to Trackless Tram. Journal of Transportation Technologies, 10, 198-213.
https://doi.org/10.4236/jtts.2020.103013

[15]   Ndlovu, V., & Newman, P. (2020a). Designing a Transit Oriented Development with a Trackless Tram System—Case Study Bulawayo. Journal of Urban Planning and Development.

[16]   Ndlovu, V., & Newman, P. (2020b). The Public-Private Partnership Procurement Approach—Zimbabwe Case. The World Bank Research Observer Journal.

[17]   Ndlovu, V., Newman, P., & Sidambe, M. (2020). Prioritisation and Localisation of Sustainable Development Goals (SDGs): Challenges and Opportunities for Bulawayo. Journal of Sustainable Development, 13, 104-118.
https://doi.org/10.5539/jsd.v13n5p104

[18]   Newman, P., Davies-Slate, S., & Jones, E. (2018). The Entrepreneur Rail Model: Funding Urban Rail through Majority Private Investment in Urban Regeneration. Research in Transportation Economics, 67, 19-28.
https://doi.org/10.1016/j.retrec.2017.04.005

[19]   Newman, P., Hargroves, K., Davies-Slate, S., Conley, D., Verschuer, M., Mouritz, M., & Yangka, D. (2019). The Trackless Tram: Is It the Transit and City Shaping Catalyst We Have Been Waiting for? Journal of Transportation Technologies, 9, 31-55.
https://doi.org/10.4236/jtts.2019.91003

[20]   Newman, P., Mouritz, M., Davies-Slate, S., Jones, E., Hargroves, K., Sharma, R., & Adams, D. (2018). Delivering Integrated Transit, Land Development and Finance—A Guide and Manual with Application to Trackless Trams. Australia’s Sustainable Built Environment National Research Centre (SBEnrc).
https://sbenrc.com.au/app/uploads/2018/10/TRACKLESS-TRAMS-MANUAL-GUIDE_email.pdf

[21]   Suzuki, H., Murakami, J., Hong, Y.-H., & Tamayose, B. (2015). Financing Transit-Oriented Development with Land Values: Adapting Land Value Capture in Developing Countries. Washington DC: The World Bank.
https://doi.org/10.1596/978-1-4648-0149-5

[22]   Willoughby, C. (2013). How Much Can Public Private Partnership Really Do for Urban Transport in Developing Countries? Research in Transportation Economics, 40, 34-55.
https://doi.org/10.1016/j.retrec.2012.06.038

[23]   Zaaijer, M. (1998). Urban Economic Restructuring and Local Institutional Response: The Case of Bulawayo, Zimbabwe.

 
 
Top